TREATMENT COSTS Tertiary treatment (coagulation-flocculation + filtration) This costs computation concerns the following units of treatment:
The treatment costs, including capital, operation and maintenance costs, have been obtained assuming a daily pro-capita discharge of 300 l/EI-d. If you want to meet the treatment cost for different values of daily pro-capita discharge, you must activate the following link. AUTOMATIC COMPUTATION COSTS OF TREATMENT
Treatment cost for daily pro-capita discharge of 300 l/EI-dThe unit treatment costs, expressed in £/m3, have been obtained with the following equations: x < 30.000 EI: y = 1818 0.0311 x x >=30.000 EI: y = 912 0.0009 x y = unit cost in £/m3 x = equivalent inhabitants (EI)
The following Table shows the unit costs for the principal capacity plant. Unit treatment costs for the principal capacity plant
|